W Resources Plc (LON: WRES), the tungsten, tin and gold mining company announced today an update on its flagship project, La Parrilla in Spain.

· MCC electrical connections complete and plant energised

· Commissioning of Spirals and Shaking table buildings underway

· First ore to new concentrator scheduled for September

The La Parrilla Concentrator Plant has commenced commissioning following the detailed installation of the Motor Control Centre (“MCC”) including all electrical connections and associated plant completion work. Commissioning of the spirals and shaking tables buildings ‘on water’ has commenced, which is an important phase prior to feeding ore through. Ore will be introduced into the circuit with first concentrate production from the new Concentrator Plant planned in September, as announced on 7 August 2019.

Michael Masterman, Chairman of W Resources commented:

“The commencement of commissioning of the new Concentrator Plant is a long-awaited event and is a major step forward for W Resources. It is important to note that commissioning ensures a streamlined start-up of the ramp-up of tungsten and tin production. The Crusher and Jig & Mill Plants are operations ready and we have maintained the low-cost nature of this impressive world class project by ensuring each phase is delivered to the highest standards as we prepare for first concentrate production in September.”

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Twitter
LinkedIn
Facebook
Email
Reddit
Telegram
WhatsApp
Pocket
Find more news, interviews, share price & company profile here for:

      Search

      Search