SSE approves final investment decision for Viking onshore wind farm

Wind Farm
[shareaholic app="share_buttons" id_name="post_below_content"]

SSE plc (LON:SSE) has approved a final investment decision for the 103-turbine, 443MW Viking onshore wind farm, in a step which will help to drive forward a green economic recovery after the coronavirus lockdown. Located in Shetland, Viking is wholly owned by SSE Renewables having been developed in partnership with Viking Energy Shetland.

Viking will harness the excellent wind conditions in Shetland which result in an estimated load factor of around 48%. Once built it will be the largest onshore wind farm in the UK in terms of annual electricity output, which is expected to be around 1.9TWh each year, therefore playing a vital role in contributing towards the UK and Scotland’s net-zero targets.

SSE now awaits the outcome of the consultation on Ofgem’s minded-to position to approve a 600MW transmission connection from Shetland to the GB mainland, expected in July 2020. Final approval from Ofgem was conditional on Viking wind farm reaching a positive final investment decision which this announcement confirms. The transmission connection is critical for Viking to proceed.

SSE’s decision is conditional on the outcome of several industry code modifications which are currently in progress. These include the code changes which facilitate the contribution from the Distribution Network Operator, SHEPD, to the cost of the transmission link. Ofgem is expected to publish a decision on these ahead of the decision on the Needs Case.

SSE’s capital expenditure on the wind farm is estimated to be around £580m, and this forms part of updated capital expenditure plans which are set out as part of SSE’s preliminary results on 17 June. Construction on the enabling works for the transmission link has started, with works on the wind farm starting late summer.

Viking is the anchor project that commercially underpins the transmission link, which will play a critical role in Shetland’s security of supply needs. Both the wind farm and the link will bring vital socio-economic benefits to the islands, opening up much needed and sustainable diversification of the Shetland economy.

Scottish Government Energy Minister, Paul Wheelhouse, said: “This is excellent news for Shetland, and for Scotland’s renewable energy and climate change ambitions. The Viking wind farm project is also a great symbol for the green recovery that the Scottish Government is determined to foster and encourage, as we move through and beyond the current Coronavirus pandemic.

“This decision is of sufficient scale to act as the trigger to unlock the much anticipated major investment in a high voltage connection from Shetland to mainland Scotland, subject to a final decision by Ofgem which we expect shortly. It is essential that the community of Shetland benefits from this project and we look forward to further news of contracts being awarded to local businesses, as well as Scotland as a whole, during the construction phase.

“I am determined that this excellent outcome should be a starting point for similar investments and connections to unlock equivalent potential and benefits on the Western Isles and in Orkney.”

Managing Director of SSE Renewables, Jim Smith, said: “Viking wind farm will help kickstart the green economic recovery, bringing much needed low-carbon investment to Shetland. In doing so, it will trigger the building of the associated transmission connection to the islands, which will itself help resolve longstanding security of supply issues on the island”.

Twitter
LinkedIn
Facebook
Email
Reddit
Telegram
WhatsApp
Pocket
Find more news, interviews, share price & company profile here for:
    SSE CEO Alistair Phillips-Davies to retire in 2025, ending an 11-year tenure that transformed SSE into a leader in clean energy and net-zero initiatives.
    SSE plc and APG advance 2GW Alpha offshore wind project in the Netherlands, aiming to commission by decade's end, enhancing sustainable energy growth.

      Search

      Search