Pensana site preparation works well underway at Longonjo

Pensana
[shareaholic app="share_buttons" id_name="post_below_content"]

Pensana plc (LON:PRE) has provided the following update on the Longonjo project:

Concrete foundations have been poured for the 316-person modular camp manufactured in South Africa for despatch to site later this month.

The on-site team, under the leadership of experienced Project Manager Kevin Botha, is continuing to make good progress with preparatory works ahead of main construction anticipated in May 2024, with cold commissioning commencing in August 2025.

An order has been placed with NCP International, a global supplier of new and refurbished comminution equipment based in South Africa, for the US$2.3 million ball mill for delivery from Johannesburg to meet the construction and commissioning timelines for the concentrator plant.

The detailed design and procurement documentation for other main long lead time or critical path items, such as the thickeners and flotation columns in the concentrator section, along with key equipment in the recovery/MREC section, such as the sulphuric acid plant, have been completed and orders will be placed with the selected vendors shortly.

Grupo Nov has completed the civils and services connections for the initial section of the 316-person modular construction camp. The US$1.3 million camp has been fabricated off site and is ready for shipment from Johannesburg to site during March 2024.

All the site access roads have been completed within the licence area. The 5,000-litre potable water tank is ready for installation to support the construction camp and the future plant facilities.

High priority is being given to community relations and in particular to the resettlement action and livelihoods restoration plans which are progressing according to plan and are being well received.

The agricultural demonstration plots are in their second year and continue to generate excellent baseline data.  They are providing the opportunity to train local farmers in the latest agricultural methods.

The mine and processing plant will be constructed from May 2024 and commissioning of the various circuits will commence in March 2025 and continue until final commissioning in April 2026.

A schedule of the expenditures is set out below.

Quarterly ExpendituresUS DollarsActivity
May – July 2024         5 044 000Civil and Earth Works
August – October 2024       18 889 000Structural and Mechanical installation
November – January 2025       32 435 000Platework and piping installation
February – April 2025       36 032 000Electrical installation
May -July 2025       36 185 000Instrumentation installation
August – October 2025       38 274 000Cold Commissioning
November – January 2026       23 096 000Hot Commissioning
February – April 2026         6 476 000Final Commissioning
Total196 432 000

Tim George, Pensana CEO commented: “The growing on-site team, supported by experienced contractor Grupo Nov, is fully operational and is well advanced with the earth works and other preparatory works ahead of the commencement of the main civils and earthworks campaigns in the weeks ahead.

We are particularly pleased with the attention to health and safety, environmental performance, the training completed on site and the continued focus on the community engagement programs. This will continue to be a priority as we build out the workforce which will increase to over 650 people on site at peak construction later this year.”

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Twitter
LinkedIn
Facebook
Email
Reddit
Telegram
WhatsApp
Pocket
Find more news, interviews, share price & company profile here for:
Pensana Plc (LON:PRE) inks a non-binding MOU with Japan's Hanwa Co. Ltd for a substantial offtake and potential investment in rare earth mining and sustainable magnet metal supply chains.
Pensana plc (LON:PRE) has been awarded a Gold Medal by EcoVadis, ranking among the top 5% of companies assessed for sustainability in the industry.
Pensana plc provides update on beneficiation test work at Sulima West deposit, showing potential for high-grade concentrate. Read more here.
Pensana plc (LON:PRE) updates on US$15 million loan facility from Angolan Sovereign Wealth Fund for Longonjo project funding, with extension talks underway.
Pensana plc (LON:PRE) reports analytical results for Sulima West laterite, showing promising grades for rare earth mineralisation. Exciting developments in exploration highlighted.

Search

Search