NQ Secures High Grade Underground Base Metals Resources

NQ Minerals plc
[shareaholic app="share_buttons" id_name="post_below_content"]

NQ Minerals plc (LON: NQMI) has announced that it has secured high grade underground base metals resources at its Hellyer mine with bonanza drilling grades.

Highlights:

· NQ to acquire additional lead/zinc/gold/silver resources and mineral rights at its flagship Hellyer Mine in Tasmania, Australia from Bass Metals Ltd (“Bass”);

· Acquisition includes 1.175 million tonnes of underground JORC Resources grading 8.6% Zinc, 4.9% Lead, 96 g/t Silver and 1.66 g/t gold (Refer to Table 1);

· These resources offer significant potential of increasing Hellyer’s overall resources to add to the 10-year mine life to its tailings reprocessing project;

· 9 well advanced exploration targets have been developed to date within the Hellyer Mining Lease and all targets are located close to pre-existing mine decline development and are within 2 km of Hellyer;

· Bonanza drilling intercepts for immediately follow up, including:

§ 20.4 metres grading 16.3% Zn, 7.2% Pb, 104 g/t Ag and 2.4 g/t Au at the Fossey East Orebody;

§ 7.0 metres grading 22.3% Zn, 9.9% Pb, 181 g/t Ag and 3.4 g/t Au at the new Mackays prospect discovery, which sits immediately adjacent to the Hellyer orebody;

· Hellyer Plant rated at 1.6 million tonnes per annum and permitted for 2 million tonnes per annum for mining and processing;

· The Hellyer plant is currently operating at 62% of its capacity, processing around 1 million tonnes a year of high-grade zinc/lead/gold/silver tailings.

London listed NQ Minerals Plc, the base and precious metals producer from its flagship Hellyer Gold Mine in Tasmania, Australia, has announced that it has signed a deal with Bass Metals Ltd (ASX: BSM) to finally secure 100% of all the mining and exploration rights to the main 1,695 hectare Hellyer Mining Lease (CML103M/87) by Bass surrendering its long standing Sublease Agreement over Hellyer’s underground base metals rights. NQ has also acquired 100% rights to the 46 km2 Mt Block permit (EL48/2003), which surrounds the Hellyer Mining Lease.

David Lenigas, Chairman of NQ Minerals, commented:

“This acquisition is truly transformational for NQ. This long-awaited deal provides real potential to radically change the long-term plans for Hellyer and the perception of NQ in the market. There is real potential to re-open the underground mining operations, adding much higher-grade ore feed to the plant over the coming years. Some of the drill intercepts near the Hellyer orebody are regarded as ‘bonanza’ grades anywhere in the world and NQ is planning to commence drilling a number of the high priority targets as soon as possible. Exploration around VHMS ore bodies, such as Hellyer, is supported by the fact that deposits of this style are often clustered and occasionally stacked at more than one stratigraphic level. The last operator of the mine discovered three significant zones of base metal mineralisation within 200 metres of the large Hellyer orebody at Fossey, Fossey East and Mackay and confirmed the significant potential for new discoveries on the leases.”

NQ recommenced operations at Hellyer a year ago with a major mine tailings retreatment operation with a stated mine life of over 10 years. These operations are now running profitably, as referred to in recent news releases.

This transaction with Bass now provides a very real opportunity for NQ to look towards re-opening underground mining operations on very high-grade base metals deposits already identified at Hellyer, providing potential to extend its operational life well beyond the current 10-year plan.

Historically, some 18.2 million tonnes of ore grading 12.2% Zinc (Zn), 6.3% Lead (Pb), 0.3% Copper (Cu), 156 g/t Silver (Ag) and 2.4 g/t Gold (Au) have been mined from the Hellyer area.

This transaction will bring to NQ’s books additional JORC (2004) resources of 1.175 million tonnes grading 8.6% Zn, 4.9% Pb, 96 g/t Ag and 1.66 g/t Au. (Refer to Table 1)

There are a number of highly notable drill hole intersections that will require early follow-up. These include:

· 20.4 metres grading 16.3% Zn, 7.2% Pb, 104 g/t Ag and 2.4 g/t Au were intersected at the Fossey East deposit; and

· 7.0 metres grading 22.3% Zn, 9.9% Pb, 181 g/t Ag and 3.4 g/t Au at the new Mackays prospect, which sits adjacent to the Hellyer orebody.

At least 9 well advanced exploration targets have been developed to date within the Hellyer Mining Lease and all targets are located close to pre-existing mine decline development and are within 2 km of Hellyer’s 1.6 million tonne per annum capacity processing plant.

Table 1: Existing Underground Resource Estimates on Hellyer Mining Lease CML103M/87

DepositJORC ClassificationTonnes ‘000zinc (%)lead (%)Copper (%)silver g/tgold g/t
Fossey and Fossey EastMeasured17512.470.51372.8
 Indicated20011.160.5941.8
 Inferred508.74.70.4992.3
 Total42511.46.30.51122.3
HellyerIndicated6406.840.4831.3
 Inferred1108.14.90.21071.5
 Total75074.10.3871.3
Mining LeaseTotal1,1758.64.90.4961.66

Note: Fossey, Fossey East and Hellyer remnant JORC 2004 resource reported to ASX by Bass Metals Ltd (ASX Code: BSM) dated 30 September 2013.

NQ’s operating entities associated with its Tasmanian operations will pay Bass Metals Ltd A$15,000 per month for 24 months and provide local minor logistics support to Bass for their continuing obligations with nearby tenements. In addition, NQ will be taking over security deposits totalling A$112,000 with the Tasmanian Government on the Hellyer Mine’s licence (CML103M/87) and the surrounding Mt Block Exploration Licence (EL48/2003). The transaction is expected to close in January 2020. The market will be advised when this transaction closes.

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Twitter
LinkedIn
Facebook
Email
Reddit
Telegram
WhatsApp
Pocket
Find more news, interviews, share price & company profile here for:

      Search

      Search