Ascent Resources Plc (LON:AST) the European focused oil & gas exploration and production company has today announced that gas production from Pg-10 is expected to commence to a local corporate consumer in the early part of April 2017. This will provide the Company with immediate revenue until the increased production under the INA contract commences.
The flowline from Pg-10 has been completed and will be connected immediately before production begins.
CEO Colin Hutchinson talks to DirectorsTalk about its operational update. Colin talks us through what’s been happening with plans around gas production & how Pg-11A is progressing. With the IPPC permit still under review at the Slovenian courts, Colin shares his thoughts on granting of the permit and also what this will allow the company to do.
Production to INA
Separately, preparations for the sale of gas to INA under the existing contract are well under way. Whilst the final treatment of the gas delivered to INA will be at their treatment plant at Molve in Croatia, the gas from Pg-10 must first be dehydrated at the Petišovci field.
The Company had intended to lease temporary equipment while the refurbishment of the existing gas separation facility (CPP) was completed. The minimum lease term for this equipment was six months and the anticipated cost was deemed higher than necessary.
Accordingly, revisions to the CPP design have been made, based on the data obtained during the Pg-10 flow test completed in February 2017. These refinements allow for a more efficient installation, which will result in both time and cost savings, without the need for the leased equipment. The refurbished plant is expected to be ready for production to INA in three months at around half of the previously budgeted cost of €1million, increasing the profit expected on the INA contract.
During the period while these works take place gas will be sold locally as noted above.
Pg-11A recompletion
The workover of Pg-11A will start in April 2017 and is expected to last around four weeks. A rig owned by our partner, Petrol Geoterm, will be used to remove and replace the tubing string. Once this work has been completed a 40 metre flowline will be laid to connect the well to the CPP.
Connection of the export line
The existing pipeline from the CPP will be connected to the existing export pipeline at MRS Lendava which is the land that Ascent acquired when it purchased Trameta doo in July 2016. The site has been cleared of obsolete equipment and made ready for the short connection to be installed. This connection has been pre-fabricated and will be installed in April.
IPPC Permit
The Company remains optimistic that the Environment Minister will soon confirm the decision of the Environmental Agency, in November 2016, that a full Environmental Impact Assessment is not required for the new processing facility.
Colin Hutchinson, Ascent Resources plc CEO, commented: “I’m delighted to report impressive progress at our asset in Slovenia which illustrates that after years of frustration and delays we are only weeks away from commercial production and the further development of the field.”