Firering Strategic’s Limeco fast-tracked towards the start of phased commissioning

Firering Strategic Minerals
[shareaholic app="share_buttons" id_name="post_below_content"]

Firering Strategic Minerals plc (LON:FRG), an emerging quicklime production and critical mineral exploration company, has announce an operational update with regards to its quicklime project in Zambia (Limeco), which is being fast-tracked towards the start of phased commissioning in Q4 2024.

HIGHLIGHTS

·    Key modifications to the first of eight kilns are nearly complete, which will significantly improve operational efficiency and lower the plant’s operating costs.

·    Aggregate crushing operation continues to perform well, supporting positive cash flow.

·    Positioned to commence production immediately on commissioning of Kiln 1 in Q4 2024 with kiln stockpile now standing at +15,000 tonnes.

·    Newly built pilot kiln performing effectively, with promising burn test results.

·    Positive off-take discussions progressing well, driven by Limeco’s strong production capacity and commitment to quality control, attracting notable market interest.

·    Updated JORC-compliant Mineral Resource Estimate anticipated in November 2024.

Yuval Cohen, Chief Executive of Firering Strategic Minerals, said: “We are delighted by the rapid progress at Limeco, including the installation works for the first gasifier, which marks a key milestone in the plant renovation strategy. Modifications to the first kiln are nearly complete, with commissioning of both the kiln and gasifier targeted for Q4 2024. Laboratory test work has also accelerated, supported by the completion of a pilot kiln, which has yielded initial quicklime (CaO) results between 92% and 94%. This progress is driving productive discussions with prospective clients, and accordingly we are optimistic about securing long-term offtake agreements.

“The upcoming two months promise to be extremely busy as we work toward the production start target, with a steady stream of news expected. This includes the release of an updated Mineral Resource Estimate as Limeco positions itself to meet the rising demand from Zambia’s growing copper production market.”

DETAILS

Limeco’s quicklime project remains on track for phased commissioning to start in Q4 2024 with critical modifications to the first of eight kilns largely complete. Key to this is the conversion of the fuel source for these kilns from Heavy Fuel Oil (“HFO”) to coal gasification, which will significantly enhance the operational efficiency and reduce operating costs of the plant.

Additionally, the aggregate crushing operation is continuing to perform very well, underpinning positive operational cashflow as well as providing an increasing stockpile for the kilns, which is now in excess of 15,000 tonnes.

Coal gasifier

The first gasifier arrived on site and is now being erected.

Figure 1: Parts of gasifier arriving at Limeco, 29 October 2024.

Figure 2: Parts of gasifier being off loaded at lime plant, 29 October 2024.

Figure 3: Erection of gasifier

Modifications to Kiln 1

Work is progressing well for the commissioning of Kiln 1 by the end of Q4 2024 with the following activities concluded or in progress:

ItemStatusComment
Discharge coneCompleted & operationalIncreased discharge opening
Rotary tableCompleted & operationalModified opening
New skip hoist brakesCompleted & operationalSingle drum changed to double
New discharge gatesNot completedAwaiting arrival on site
New burner portsNot completedArrived & being installed
Feed conveyor to skip hoistCompleted & operational
Skip hoistCompleted & operational
Pan conveyorCompleted & operational
Roller crusherCompleted & operational
Bucket elevatorCompleted & operational
Silo discharge endNot completedWork in progress
Modified exhaust stackCompletedInstalled on 30 October 2024

Figure 4: View of refurbished hoist structure (blue) and refurbished skip (orange).

Coal storage facility

Work on the coal storage facility, from where the coal will be conveyed to the coal gasifier, is 40% completed.

Figure 5: View of incline ramp from coal storage facility to coal gasifier.

Crushing plant

The newly installed impact crusher is performing well with over 60,000 tonnes of limestone crushed.  The kiln feed, sized -90mm to +60mm, is stockpiled near the lime plant and now totals 15,000 tonnes. Furthermore, aggregate production from the minus 60mm stream is also going well and contributing 50% to Limeco’s positive operational cashflow.

Figure 6: View of part of the kiln feed with lime plant in the background.

Laboratory

The recently constructed pilot kiln is performing well with burn tests giving good results; initial test results showed available quicklime ranging between 92% and 94%.

Figure 7: Burnt limestone from the pilot kiln awaiting further testwork to determine available quicklime (CaO).

Mineral Resource Estimate

Earthlab Exploration and Mining Consulting (“Earthlab”) has been engaged by Firering to update the current Mineral Resource Estimate (“MRE”) of 73.7Mt @ 95.3% CaCO3  produced by Golder Associates in October 2017. This update, incorporating data from the recently awarded 392.51 hectare exploration licence adjacent to Limeco’s current licence (see RNS dated 3 September 2024), has the potential to increase the MRE by between 60Mt to 70Mt at similar grades. Earthlab’s updated JORC compliant report is expected in November 2024.

Long-term offtake agreements

Discussions are advancing with clients across various sectors for long-term offtake agreements.  This includes negotiations with local and regional industries currently reliant on imported quicklime, principally from South Africa.  Limeco’s robust production capacity, combined with its commitment to quality control, is generating considerable market interest.

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Twitter
LinkedIn
Facebook
Email
Reddit
Telegram
WhatsApp
Pocket
Find more news, interviews, share price & company profile here for:
Firering Strategic Minerals' Vassilios Carellas discusses Limeco's quicklime plant's capacity, limestone processing, and operational cash flow in an exclusive interview.
Firering Strategic Minerals plc (LON:FRG) advances its Zambian quicklime project, with its first kiln commissioned, signaling promising investor opportunities.
Firering Strategic Minerals plc (LON:FRG) is advancing in quicklime production and critical mineral exploration, enhancing value for shareholders.
Firering Strategic Minerals (LON:FRG) begins commissioning the first kiln at its Limeco quicklime project in Zambia, marking a key production milestone.
Discover Firering Strategic Minerals' maiden JORC-compliant mineral resource estimate for its Quicklime project in Zambia with insights from Vassilios Carellas.

Search

Search