Edenville Energy continues to ramp up production with 80% increase in October

Edenville Energy
[shareaholic app="share_buttons" id_name="post_below_content"]

Edenville Energy Plc (LON:EDL) has today provided an update regarding the Company’s Rukwa Coal Project in southwest Tanzania for the month of November 2021, as it continues to ramp up production.

November 2021 highlights

· 80% Increase in Run of Mine (“ROM”) coal production from October 2021 level

· 10% Increase in washed coal production from October 2021 level

· Approximately 1,000 tonnes of washed coal sales

· Orders of 3,600 tonnes of coal for December 2021 delivery confirmed from two largest customers

In November 2021, the Company mined 4,026 tonnes of ROM coal versus 2,240 tonnes in October 2021, representing an 80% increase.  Approximately 1,125 tonnes of washed coal was processed through the Company’s wash plant, representing an increase of 10% from the October 2021 figure of 1,024 tonnes, which had benefited from historic stockpiles.  A further 18,690 tonnes of waste was also moved, opening up greater access to the coal deposit for future mining.

November’s production would have been significantly higher had it not been for extended mechanical issues with the main excavator, which was unable to be used for mining for 15 days whilst initial repairs were made and it was subsequently used for the installation of culverts, and the clearing of drainage channels, to prepare the site for the wet season.  These operations have been completed and the excavator has recommenced full mining operations.  Assuming the excavator is operational throughout December 2021 the Company believes it should be able to improve substantially on November’s ROM coal production figures.

Approximately 1,000 tonnes of washed coal was sold during November 2021, with 200 tonnes remaining in stockpile.  A combined order of 3,600 tonnes of washed coal has been reconfirmed by the Company with its two largest existing clients for December 2021, with the expectation of ongoing monthly orders of circa 3,600 tonnes per month thereafter.  Discussions remain ongoing with respect to additional contracts with new potential customers.  Further updates will be announced as appropriate.

Alistair Muir, CEO of Edenville Energy, commented:

“November 2021 was both positive and frustrating.  On the one hand ROM production continued to improve, but sadly operations were hampered by the excavator being offline for half of the month.  The issues have been addressed and we look forward to continuing our progress on the mining front.  As production becomes more stable we would expect to improve the recoveries from ROM to washed coal through the plant.  Our sales book continues to improve and we are also now receiving unsolicited approaches from potential customers.”

We’ll keep you in the loop!

Join 1,000's of investors who read our articles first

We don’t spam! Read our privacy policy for more info.

Twitter
LinkedIn
Facebook
Email
Reddit
Telegram
WhatsApp
Pocket
Find more news, interviews, share price & company profile here for:

      Search

      Search